Updating Calendar for a future non working day redistributes

General discussion on illustration, art, and the business of same.
Williamhawk
Posts: 62
Joined: Sat Sep 09, 2017 10:34 pm

Updating Calendar for a future non working day redistributes

Postby Williamhawk » Thu Oct 05, 2017 11:35 pm

Hello
We are using MS Project 2007 professional SP3
When want to change 11/12/2018 and other veteran's day's for 2019 and 2020 as non working as it has become a holiday in our company.
The issue is that when we do this it re-distributes actuals that have occurred in the past. It keeps the total but from last week and then back through time actuals get redistributed. Our timephased area is by weeks and we gather actuals from resources and post per week. we can see it changing when we go to csc task usage.
We don't want those actuals changing. Is there an option setting
Any way to keep it from doing that just because we want to change non working time that is in the future?

I didn't find the right solution from the internet.